Project Update – Phase 2B Dartford (February 2025)

The finish line is in sight for the Dartford Town Centre Regeneration Phase 2b Project, with the final area of paving being laid to the North-West corner and new intelligent traffic signals being installed by Telent Technology Services Ltd.

In the coming weeks, the road will be under a night closure for around ten shifts to be planed out, regulated and then resurfaced bringing the works to a conclusion.

Woodley Coles have provided QS support to Dartford Borough Council working alongside Main Contractor Henderson & Taylor to deliver the scheme.